| 2010 Restoration Project | ||||||
| Additional Carpentry | ||||||
| 2 & 4 Arnold Drive, 8, 9, 10, 11, 12 & 14 Russell Drive and 1, 2, 3, 4, & 5 Stillwell Drive. | ||||||
| Base Carpentry Contract for Russell | $20,000.00 | |||||
| Proposed Additional Work: | Inspected (Mark&Jen) |
Sent to Board | Board Approved | |||
| 8A Russell | lower left side corner;
replace bad OSB Board; flash & install new clapboards |
$950.00 | x | 4/29 | 4/29 | |
| 8A Russell | front frame; repace 4x4 frame | $750.00 | x | 4/29 | 4/29 | |
| 8A Russell | deck connection | $1,200.00 | x | 4/29 | 4/29 | |
| 8D Russell | front frame; clalpboards; sheathing; trim | $1,400.00 | x | 4/30 | 5/3/2010 | |
| 9A Russell | front entrance' 10x5 area;
sheathing; clapboards; trim; tyvek |
$1,500.00 | x | 5/10 | 5/11/10 | |
| 9A Russell | right side of slider; 4x7
area; sheathing; insulation; tyvek; clapboards; trim |
$1,200.00 | x | 5/7/10 | 5/7/2010 | |
| 9A Russell | 1st fl to middle of 2nd;
dry rot; sheathing; insulation |
$5,800.00 | x | 6/1/10 | 6/1/2010 | |
| 9D Russell | front window area; sheathing; tyvek; clapboards | $1,100.00 | x | 5/6/2010 | 5/7/10 | |
| 9D Russell | front left side; 10x20;
sheathing; tyvek; clapboards; trim |
$3,200.00 | x | 5/10 | 5/11/10 | |
| 9D Russell | deck connection; sheathing
under deck; tyvek; clapboards |
$1,600.00 | x | 5/10 | 5/11/10 | |
| 9A Russell (gable) | replace clapboards; 64 sq ft of sheathing; tyvek; new clapboards, new window trim | $9,800.00 | x | 5/7/10 | 5/7/2010 | |
| 9A &B Russell | front' 25x10; strip; clapboards; tyvek; trim; | $2,800.00 | x | 5/10 | 5/11/10 | |
| 9B Russell | rear; left of slider; 3x10;
clapboards, sheathing; trim; tyvek |
$1,200.00 | x | 5/7/10 | 5/7/2010 | |
| 9B Russell | front corner; 2x10 area;
sheathing; clapboards; trim |
$675.00 | x | 5/7/2010 | 5/7/2010 | |
| 9D Russell | gable; lower corner; 1st
floor sill, plywood; insulation; framing |
$4,600.00 | x | 5/24/2010 | 5/24/2010 | |
| 10A Russell | rt side gable; 2nd fl; trim, clapboards; flash & tyvek | $3,600.00 | x | 5/6/10 | 5/7/10 | |
| 10A Russell | front near entry; sheathing; clapboards | $1,400.00 | x | 4/30 | 5/3/2010 | |
| 10A Russell | rear; remove 20 ft section
that is not working properly; re-install new section; replace rotted facia & trim |
$1,800.00 | x | 5/7/10 | 5/7/2010 | |
| 10D Russell | deck connection; reframe;
sheathing; flashing; clapboards; trim |
$1,200.00 | x | 4/30 | 5/31/2010 | |
| 11A Russell | gable; 20x30 area; strip; tyvek; trim; clapboards | $6,500.00 | x | 5/20/10 | 5/20/10 | |
| 11A & B Russell | front; 10x25; strip; tyvek;
clapboards; trim, sheathing |
$2,800.00 | x | 5/18 | 5/19/10 | |
| 11B Russell | front right; 4x15; sheathing; tyvek; clapboards; trim | $1,450.00 | x | 5/10 | 5/11/10 | |
| 11B Russell | rear; 10x4; sheathing; clapboards; trim; tyvek | $1,650.00 | x | 5/10 | 5/11/10 | |
| 11C & D Russell | front wall; 10x25; strip; tyvek; clapboards; trim | $2,500.00 | x | 5/18 | 5/19/10 | |
| 11D Russell | deck connection; soffit replacement | $1,400.00 | x | 5/7/2010 | 5/7/2010 | |
| 11D Russell | 15x10; sheathing; insulation; clapboards & trim | $2,500.00 | x | 5/10 | 5/11/10 | |
| 11D Russell | left front; 4x12; frame; clapboards; trim | $1,600.00 | x | 5/10 | 5/11/10 | |
| 11D Russell | front corner; sheathing; clapboards; trim | $850.00 | x | 5/7/2010 | 5/7/2010 | |
| 12A Russell | front right side corner; 6x6; clapboard; trim | $950.00 | x | 5/6/2010 | 5/7/2010 | |
| 12A & B Russell | rearwall; 25x10 clapboard replacement; deck connection @ A; entry way at A | $4,600.00 | x | 5/20/10 | 5/20/10 | |
| 12B Russell | front near gutter; 15x5
area; framing; trim; clapboards; |
$2,400.00 | x | 5/18 | 5/19/10 | |
| 12C&D Russell | 20x10 back wall;
clapboards; trim; fascia behind gutter; replace gutter |
$3,400.00 | x | 5/18 | 5/19/10 | |
| 12D Russell | right side lower corner;
new sheathing; clapboards 15x10; deck connection; |
$3,600.00 | x | 5/18 | 5/19/10 | |
| 14A Russell | front right corner; 7 x 6
area; sheathing; clapboards; trim |
$1,100.00 | x | 5/5/10 | 5/5/2010 | |
| 14B Russell | deck connection; no clapboards | $950.00 | x | 5/5/10 | 5/5/2010 | |
| 14B Russell | rear inside corner wall;
2x5 area; sheathing; clapboards |
$550.00 | x | 5/5/10 | 5/5/2010 | |
| 14C Russell | rear; 1x7 sheathing; clapboards | $575.00 | x | 5/6/10 | 5/7/2010 | |
| 14C Russell | rear; 2x11; clapboards, trim; left of slider | $950.00 | x | 5/6/10 | 5/7/2010 | |
| 14D Russell | gable wall; 20x30 area; strip; tyvek; clapboards; trim | $6,000.00 | x | 5/5/10 | 5/5/2010 | |
| 14D Russell | front; 15x10 area; strip; tyvek; clapboards; trim | $1,800.00 | x | 5/7/10 | 5/7/2010 | |
| 14D Russell | deck connection; rear corner; sheathing; clapboards; trim | $1,400.00 | x | 5/20/10 | 5/20/10 | |
| Russell Total: | $115,300.00 | |||||
| 2A Arnold | door frame; 4x4 area | $950.00 | x | 6/17/10 | ||
| 2A Arnold | right gable; 10x25; framing; sheathing; clapboards | $6,200.00 | ||||
| 2B Arnold | left corner; 7x2; sheathing; clapboards | $1,200.00 | x | 6/17/10 | ||
| 2C & D Arnold | back rear side of chimney; 7x7 area | $1,100.00 | x | 6/17/10 | ||
| 2C Arnold | front & rear cheek wall ; 20X40 area; trim; clapboards | $8,000.00 | ||||
| 2C Arnold | front 11x2; trim; clapboards | |||||
| 4A&B Arnold | 15x20; clapboards, trim, sheathing | $3,500.00 | ||||
| 4B Arnold | front & rear cheek
walls; clapboards; sheathing 20x40 |
$8,500.00 | ||||
| 4C Arnold | left side of chimney; 2x7 area & sheathing | $650.00 | x | 6/17/10 | ||
| 4D Arnold | 10x40 front; clapboards; trim | $4,500.00 | ||||
| Arnold Total : | $34,600.00 | |||||
| 7A Griswold | total re-build with electrician | $27,467.00 | ||||
| 7A Fillmore | total re-building | $16,100.00 | ||||
| $193,467.00 | ||||||